77. Within 90 days of receiving a complete project the Minister, in a written communication with the promoter, confirms or rejects
(1)  the project’s eligibility, in accordance with the eligibility conditions set out in Chapter I of Title II;
(2)  the validity of the initial inventory and the baseline scenario.
When a project’s eligibility is confirmed by the Minister, a project code is assigned and forwarded to the promoter.
M.O. 2022-11-17, s. 77.
In force: 2022-12-29
77. Within 90 days of receiving a complete project the Minister, in a written communication with the promoter, confirms or rejects
(1)  the project’s eligibility, in accordance with the eligibility conditions set out in Chapter I of Title II;
(2)  the validity of the initial inventory and the baseline scenario.
When a project’s eligibility is confirmed by the Minister, a project code is assigned and forwarded to the promoter.
M.O. 2022-11-17, s. 77.